dc.description.abstract | In Ethiopia the number of road construction projects is increasing from time to time. However, it
becomes difficult to complete projects in the allocated cost and time. Thus, time and cost overrun
are some of the major problems in Ethiopian road projects. Therefore, this research was carried
out to dig-out information on the most important factors that contribute time overrun on the road
construction projects in Ethiopia. The objective of this study was to identify the causes of delays,
based on a study of completed road projects and rate the extent of time overruns of the road
construction projects in Ethiopia. The research used purposive sampling technique and analyzed
data using SPSS & Relative Importance Index(RII) to rank the delay factors. A total of fortyfive
factors and seven groups that contribute to the causes of delay. From the investigation study
found out that: improper planning, unforeseen site condition, delay removal of obstruction &
poor site management as important factors causing delay. The questionnaire survey was
distributed to the three main parties of the construction industry; employers (Ethiopian Road
Authority), contactors and consultants. Based on the survey findings the top fifteen delay factors
contributing to road construction project are, failure to remove obstruction & give site, award
project to lowest bid price, improper planning, rework due to errors during construction, low
productivity of labor, progress payment delay by owners, design modification, poor site
management, inaccurate time estimation, sub-contractor delay, inaccurate cost estimation, low
skill of manpower, poor resource management, interference of owner & liquidated damage,
ranked from the perception of the stakeholders (owner, consultants & contractors). | en_US |
dc.language.iso | en | en_US |
dc.publisher | St.Mary's University | en_US |
dc.subject | road project, delay factors, Road construction project stake holders | en_US |
dc.subject | time overrun | en_US |
dc.title | ANALYSIS OF FACTORS CONTRIBUTING TO TIME OVERRUNS OF ROAD PROJECTS: THE CASE OF ETHIOPIAN ROADS AUTHORITY | en_US |
dc.type | Thesis | en_US |
Appears in Collections: | Project Management
|