dc.description.abstract | A construction project is commonly acknowledged as successful when the aim of the project is
achieved in terms of predetermined scheduled time, within budget, standard quality and specifications
to meet stakeholders’ satisfaction. In Ethiopia, the number of housing construction projects is
increasing from time to time. However, it becomes difficult to complete projects in the allocated cost
and time. Many projects experience time and cost overruns and thereby exceed initial contract time and
budget. It is therefore, this research was conducted to identify factors that cause time and cost overruns
for condominium house construction project at Addis Ketema sub city housing development project
office. A comprehensive literature review was reviewed to generate a set of factors believed to affect
project time and cost overruns. A total of 55 questionnaires were distributed to three key groups of
project participants; namely owner, consultant and contractors. The survey focused on identifying and
ranking in order of importance the main factors causing project delay and cost overruns and their
effects on housing projects in the sub city. The data from the questionnaire was analyzed statistically.
Relative important index method was used to foundout the most significant factors affecting time and
cost overruns. Spearman’s correlation coefficient analysis was also used to evaluate the degree of
agreement /disagreement of the respondents on the causes of time and cost overruns. The result of the
study revealed that the main causes of delay and cost overruns in construction of condominium house
projects were financial problem during construction, inadequate funding of project, delay in payment
for completed works, incomplete drawings and documents, slowness of decision making, costs
underestimation, delay in delivery of construction materials, slowness in giving instructions, unrealistic
contract durations and project scope definition for time overrun and shortage of materials, cost
underestimation, inaccurate material specifications, lack of financial management and planning, high
transportation cost, lack of experienced project managers, lack of experienced consultants and
unavailability of competent staffs, dependency on imported construction materials, suspension of
works and different consultants for design, supervision and contract administration works for cost
overruns. The most common identified effects of project time and cost overruns were time claim, cost
claim, frustration on stakeholders, the incompetency of project participants, dispute among
stakeholders, arbitration, total abandonment of the project, litigation, weakens the growth of the
construction industry and affects, in a negative way, the rate of national socio- economic development
of the country. | en_US |
dc.language.iso | en | en_US |
dc.publisher | St.Mary's University | en_US |
dc.subject | Construction Industry | en_US |
dc.subject | condominium house, | en_US |
dc.title | FACTORS AFFECTING TIME AND COST OVERRUNS IN HOUSING CONSTRUCTION: THE CASE OF ADDIS KETEMA SUB CITY HOUSING DEVELOPMENT PROJECT | en_US |