dc.contributor.author | TAYE, MERID | - |
dc.date.accessioned | 2017-01-06T09:36:00Z | - |
dc.date.available | 2017-01-06T09:36:00Z | - |
dc.date.issued | 2016-09 | - |
dc.identifier.uri | http://hdl.handle.net/123456789/2708 | - |
dc.description.abstract | In DCE the number of construction projects is increasing from time to time. However, it
becomes difficult to complete
projects in the allocated cost and time. Taking this into
consideration, time and cost overruns is one of the major problems in the construction
proje
cts. Therefore, this research i
s carried out to make assessment on the factors that
cause time and cost
overruns of construction projects, their effects and resolutions.
Questionnaire survey together with desk study was used to collect
data on time and cost
overruns
.
Desk studies of 10 completed construction projects were investigated, and from the
analysis
it was found that 100% of the construction projects suffered by both time and cost
overruns. The rate of time overrun ranges from a minimum of
13
% to the maximum of
181
% of the contract
time
, and cost overrun ranges from a minimum of 1% to the
maximum of
4
7
% of the contract amount.
A total of 48 questionnaires were distributed and collected from DCE managers, team
leaders and experts. From the analysis of the questionnaire response, th
e top main
significant causes of time
and cost
overrun
s
are
less emphasis
to planning (MS: 2.92), poor
contract management (MS: 2.88) and
p
oor pre planning process (MS: 2.88)
.
The top
ranked effects of time and cost overruns identified by this research are
the contribution of
the construction industry to the growth of national
economy of the country will be less
(MS: 2.75), delayed payments to contractor (MS: 2.75) and inability to deliver value for
money (MS: 2.67)
.The top ranked resolution
methods
recognized by the respondents are
timely progress
control, schedule control, c
ost control, resource control by comparing with the completion
date and cost (MS: 3.33), a
ssign competent personnel (MS: 3.13) and effective strategic
planning (MS: 3.00)
.
Finally, the study recommended DCE to
have committed leadership and management,
timely decision process, advanced contract and project management, systematic control
mechanism and effective and efficient strategic planning and management. | en_US |
dc.language.iso | en | en_US |
dc.publisher | St. Mary's University | en_US |
dc.subject | Time Overrun | en_US |
dc.subject | Cost Overrun | en_US |
dc.subject | Cause | en_US |
dc.subject | Resolution | en_US |
dc.subject | Effect | en_US |
dc.subject | Business Administration | en_US |
dc.title | Assessment of Time and Cost Overruns in Construction Projects (Case Study at Defense Construction Enterprise) | en_US |
dc.type | Thesis | en_US |
Appears in Collections: | Business Administration
|